Regus

commercial fitout case-study1

Regus Dublin Airport

MAIN CONTRACTOR:All Systems Commercial Fitouts Ltd
Value: €134,000.00
Client: Regus Dublin Airport
Programme: 6 Weeks
Start/Finish:17.01.2017 – 28.02.17

 

Scope of Works:

  • Removal of existing partitions in Meeting room areas.
  • Construction of new Glazed partitions including decoration.
  • Slab existing demountable partitions in 3nr meeting rooms to take Vinyl images.
  • Remove ceiling grid to expose services and concrete structure in Co Working Area.
  • Remove existing carpet tiles and install new 14mm semi solid floor in Co Working area.
  • Installation of new Kitchen in Co Working area.
  • Remove existing kitchen on the 3rd floor and turn into office space.
  • New mechanical and electrical installations in certain areas.
  • Create a print station area in the 3rd floor corridor.
  • Divide office 503 on the 5th into two offices spaces.
  • Assist Network 2000 in data alterations throughout 3rd, 4th and 5th
  • Assist Salto on installation of door access systems throughout 3rd, 4th, 5th floors