The Arc Arena

  • Home
  • /
  • The Arc Arena

The Arc Arena

MAIN CONTRACTOR: All Systems Commercial Fitouts
Value: €1,250,000.00
Client:  Melcorpo
Size: 13,000 square feet

 

Summary of Project:

After the successful completion of the Arc Cinema, neighbouring unit, All Systems were thrilled to be selected once more as the main contractor for the next phase of Melcorpo’s project – The Arc Arena. Located in Navan, Co. Meath, the Arc Arena project included the construction of an eight nine lane bowling alley, pizzeria and arcade. This project was a huge undertaking with structural alterations required to the building. Our dedicated team once again brought our clients vision to life transforming a bare concrete space into a buzzing hub of activity for the Navan community.

DESIGN & PM: The Building Consultancy

PROGRAMME: 16 weeks

Scope of Works:

  • Demolition of former play centre to include changes in floor levels.
  • Structural alterations / new ground floor slab.
  • Full internal refurbishment and fitout of 8 no. bowling lanes, commercial kitchen, reception, toilet block, back of house areas, storage areas.
  • Front façade reconfiguration and refurbishment.
  • Ceilings- Part exposed soffit, part plasterboard, part grid.
  • Full mechanical & electrical installation works.
  • New vinyl & carpet flooring finishes.
  • Decoration of interior and selected exterior surfaces.
  • Installation of joinery units.